Pile installation monitoring
Pile Installation Monitoring for Driven, Helical and Micropiles
Every driven pile has a story told by its blow counts. Our inspector records it pile by pile, checks it against the driving criteria the engineer set, and flags the pile that stops short, runs long, or drives soft before the rig moves to the next one.
- Covers
- Steel H-piles, pipe piles, precast concrete piles, timber piles, helical piles, micropiles
- Checked against
- Pile schedule, driving criteria, hammer submittal, specification tolerances
- Deliverable
- Pile-by-pile driving logs, location and plumbness records, nonconformance log
- Code basis
- IBC Section 1705.7 (driven) and 1705.9 (helical)
- Standards
- IBC 1705.7 · IBC 1705.9 · ASTM D4945 (when paired with dynamic testing)
- Dispatched from
- Sugar Land, TX headquarters · 27 regional hubs
- Often paired with
- Dynamic Pile Testing (PDA)
Static Pile Load Testing
Pile QA/QC Programs
All deep foundation services - Call us
- (346) 420-5425
What the inspector records on every driven pile
Pile identification, type, size, and length delivered; hammer make, model, and operating stroke or energy; blow counts per foot of penetration and the final set; tip elevation and cutoff elevation; location and plumbness against the plan; splices; and any obstruction, damage, or interruption in driving.
The final blow count is compared with the driving criteria from the engineer's wave equation analysis or the test pile program. A pile that reaches tip elevation without the required resistance, or refuses well above it, is reported the same day with the record the engineer needs to decide: redrive, restrike, extend, or add a pile.
- Hammer and cushion checked against the approved submittal before production driving
- Pile material verified against mill certifications or precast plant records
- Splices checked for alignment and weld or mechanical connection per the detail
- Heave and relaxation checks on restrike when the specification calls for them
Helical piles and micropiles
For helical piles we record installation torque against depth, the final torque used for capacity, helix configuration, and termination depth. For micropiles we record drill depth, casing and bar details, grout mix, grout volume, and grout cube samples for strength testing.
Indicator and test piles
The first piles on a site set the rules for the rest. We monitor indicator and test piles in full, coordinate dynamic or static load tests on them, and help translate the results into the production driving criteria the engineer issues.
What you receive
Deliverables
- Pile-by-pile driving log with blow counts per foot and final set
- Hammer and equipment verification record
- Tip, cutoff, location, and plumbness record for each pile
- Daily field report with photos
- Nonconformance log with the engineer's disposition for each item
Who buys it
Built for
- Owners and developers who need IBC special inspection of driven deep foundations
- Geotechnical engineers of record who need field records against their driving criteria
- General contractors and pile driving subcontractors who need an independent record
- Industrial plant and tank foundation projects on the Gulf Coast
Related CMT services
FAQ
Pile Installation Monitoring: questions buyers ask
Does every pile need a full-time inspector?
The statement of special inspections decides. IBC Table 1705.7 lists observation of driving operations and recording of resistance and elevations as continuous tasks, so in practice the inspector is at the rig whenever production piles are driven.
What happens when a pile does not meet the driving criteria?
We record it, notify the contractor and engineer the same day, and log it as a nonconformance. The engineer of record dispositions it, for example restrike after setup, drive deeper, splice and extend, or add a pile, and we record the remedy when it is done.